On April 27, Mr. Duong Quang Dien, Permanent Deputy Director of Long Thanh Airport Project Management Board, said that the construction of Long Thanh Airport project will continue during the 30-4 and 1-5 holidays.
Workers work continuously during the 30-4 holiday
|
Accordingly, on the project’s construction site, the contractors have mobilized nearly 5,000 cadres, engineers, and workers, along with thousands of equipment and machinery to construct the project’s packages.
During the holidays, the contractors will coordinate with the Board to arrange a suitable construction frequency.
Specifically, at the construction site, workers and engineers still work in 3 shifts and 4 groups, spread across many items such as passenger terminals, connecting roads, taxiways, runways, and aprons.
Long Thanh airport control tower reaches more than half of the design height
|
During the day, they focus on iron, steel, digging, filling soil, laying sand, and making floors. From around 4 pm to the next morning, the passenger terminal area, runway… will be cast with cement concrete.
For the two most important packages of the project, which are the construction of the runway and passenger terminal, the contractors are focusing on the construction of crushed stone and concrete.
For the passenger terminal project, contractors are focusing on casting the concrete floor of the first floor of the project.
Nguyen Tuan