The decision has been made to split the project timeline into two components: Component 1 will focus on land clearance and resettlement, expected to take five years, while Component 2 will involve the construction of the airport with a contract duration of 47 years, divided into two phases. Phase 1 of the project commenced in 2021, and Phase 2 is anticipated to begin in 2028.

Specifically, the time allocated for the approval and design process, as well as the selection of contractors, is one year. The operation, exploitation, and capital recovery phase is expected to last for 43 years and 11 months. The construction duration for Phase 1 is estimated at two years and one month, while Phase 2 is planned to be completed within two years during the operation, exploitation, and capital recovery phase of the project. It is important to note that the airport will remain operational during the construction of Phase 2, ensuring no impact on the financial plan.

The airport’s land requirement remains unchanged at approximately 371 hectares. However, the decision emphasizes that land clearance will be completed in full during Phase 1 and is targeted for completion by 2025. Phase 1 will cover an area of 295 hectares, while Phase 2 will encompass nearly 76 hectares.

The preliminary total investment for the project remains at nearly VND 7,000 billion, but with adjustments made to the investment levels in each phase. Specifically, the investment for Phase 1 is nearly VND 4,300 billion, an increase of over VND 111 billion compared to the initial plan. This includes approximately VND 555 billion for land clearance and resettlement, and an estimated VND 3,700 billion for the construction of the airport. Conversely, the investment for Phase 2, which involves the construction of the airport, will be reduced by VND 111 billion from the initial plan, resulting in a total of over VND 2,600 billion.

The capital structure has also undergone adjustments. According to the decision, Phase 1 requires nearly VND 2,200 billion from the investor (including owner’s equity and credit capital), while the state will contribute approximately VND 2,100 billion. Similarly, during Phase 2, the investor and the state will contribute over VND 1,300 billion each, with the state’s portion being self-balanced by the locality during the 2026-2030 period.

Overall perspective of Sa Pa Airport Project

Tu Kinh

You may also like

The Road Less Traveled: Navigating the Fourth Ring Road’s Construction Conundrum

Under directives from the Chairman of the Hanoi People’s Committee, the entire Ring Road 4 passing through Hanoi was to be cleared by the end of 2023. However, despite the one-year extension, many districts have failed to meet this deadline, causing delays in the project’s progress.

The Periphery Project’s One-Year Delay: Still a Mixed Bag

In a bid to expedite the process of land clearance for the Ring Road 4 – Capital Region (Ring Road 4) project, the Chairman of the Hanoi People’s Committee had set a deadline of December 31, 2023, for districts with the project passing through to complete the task. However, as of December 2024, a year later than the initial deadline, the construction site for the Ring Road 4 project remains a patchwork of cleared and uncleared land, hindering the project’s progress.

The Smallest Province in Vietnam Achieves an ‘Unprecedented Feat’ with the Ministry of Public Security’s Airport Project Worth nearly 900 Billion VND: Unveiling the Secrets Behind this Success Story

Chairman of the Provincial People’s Committee Vuong Quoc Tuan praised the achievements of the airport project, stating that it has accomplished unprecedented feats.

The Ultimate Traffic Interchange: Unveiling the Largest Expressway Interchange in the Western Region

On the morning of November 20, Deputy Prime Minister Tran Hong Ha, along with a delegation, inspected the construction site where two major expressway projects, Can Tho-Ca Mau and Chau Doc-Can Tho-Soc Trang, intersect.

The Road to Progress: Unblocking a 6-Trillion VND Project After 16 Years

The construction project for the southern axis road in Hanoi (formerly Ha Tay province) has been lagging in its progress. Despite the time that has passed, this project has taken 16 years and is yet to be completed.