The Hoa Lien – Tuy Loan Expressway is expected to open for technical operations on August 19th – Photo: Construction Newspaper
Deputy Minister of Construction, Nguyen Viet Hung, recently inspected the construction site of the Hoa Lien – Tuy Loan Expressway, which passes through Hoa Vang district, Da Nang city.
Aiming for an August 19th Opening
Mr. Le Thanh Binh, Deputy Director of the Ho Chi Minh Road Project Management Board, stated that the local authorities have handed over the entire cleared land for the main expressway. Regarding the access roads and cross roads, there are still five households that need to relocate, and the Board is working with the local government to resolve this issue.
Currently, the project progress has reached about 60% of the plan, focusing on the following items: roadbed excavation; K95 and K98 embankment construction; various types of crushed stone and asphalt concrete construction, basically meeting the requirements.
Following the directives of the Prime Minister and the Ministry of Construction, the Ho Chi Minh Road Project Management Board has instructed the functional units and contractors to re-establish the progress, with a high determination to achieve the goal of opening this expressway on August 19th; and completing the entire project by November 2025.
According to Mr. Ta Gia Manh Hung, Director of the Hoa Lien – Tuy Loan Expressway Project Management Board, the remaining construction volume on the main line is over VND 200 billion. With three rolling chains, the contractors are striving for a minimum daily output of VND 3-4 billion. “We have requested the contractors to establish a progress chart and sign a commitment to tightly control this peak period,” said Mr. Hung.
After inspecting the construction site, Deputy Minister Nguyen Viet Hung noted that the project is entering its peak period and is about to reach its goal. The remaining site clearance and material issues have been basically resolved by Da Nang city. The Ho Chi Minh Road Project Management Board and the contractors need to continue to promote the spirit of “overcoming the sun and winning against the rain”, working in “3 shifts and 4 teams” to closely monitor the progress and control the project’s quality, ensuring the goal of opening the expressway on August 19th, celebrating the 80th anniversary of National Day and 80 years of tradition in the transport industry.
Regarding the remaining site clearance issue for the access roads, the Deputy Minister requested the investor and contractors to proactively coordinate with the local government to resolve this issue immediately in May, completing the synchronous access roads in November.
The Hoa Lien – Tuy Loan Expressway project is 11.47 km long, passing through Hoa Lien, Hoa Nhon, and Hoa Son communes of Hoa Vang district, Da Nang city, with a total investment of over VND 2,100 billion.
The project is invested by the Ho Chi Minh Road Project Management Board, which started in September 2023 and is expected to be completed by November 2025 according to the contract.
There is one construction package for this project, which is implemented by the Joint Venture of Truong Son Construction Corporation – Highway Construction Corporation 5 JSC – 17 Sole Member Limited Liability Company.
Praising the Top Seven Regions with Outstanding Disbursement Rates
The Government Office has issued Notification 223/TB-VPCP conveying the conclusions of Deputy Prime Minister Tran Hong Ha’s meeting with ministries, central agencies, and local authorities of Task Force No. 2. The meeting aimed to address challenges, expedite capital disbursement, and boost public investment in 2025.
Unleashing the Potential: Quang Tri’s Coastal Project on Track as Land Hurdles Cleared
The province of Quang Tri is currently embarking on numerous large-scale projects, including several key transportation initiatives. However, some of these ventures are facing challenges with funding and land acquisition. The local authorities are focused on resolving these issues to accelerate the progress of these projects and ensure their successful completion.
The Hanoi Eviction Project: Relocating 12 Institutions and Compensating Ho Guom Lake Residents
The Hanoi authorities have approved a plan to relocate the offices of 12 agencies and implement a compensation mechanism for residents within the scope of the Hoan Kiem Lake Eastern Rehabilitation Project. This ambitious project aims to transform the area surrounding the eastern shore of Hoan Kiem Lake, offering a new vision for the city’s future.