The leadership of the People’s Committee of Nam Dinh province recently held a meeting to evaluate and accelerate the progress of Xuan Thien Group’s projects in the Green Island area (Nghia Hung district).
According to a report by the People’s Committee of Nghia Hung district, the land clearance work for the three integrated steel projects invested by Xuan Thien Group has achieved positive results, basically meeting the conditions to commence the projects as planned.
Among the projects, the Xuan Thien Nam Dinh Precast Concrete Components Factory has handed over 100% of the land area to the investor for implementation.
The Xuan Thien Nghia Hung Green Steel Factory, spanning 84 hectares, has reclaimed the entire area, with the People’s Committees of the communes managing and ready for handover.
The Green Steel Factory No. 1, covering approximately 285 hectares, has reclaimed 98% of the area so far.

Project location.
Regarding land lease procedures, the Xuan Thien Nam Dinh Precast Concrete Components Factory has been granted land lease and received the land use right certificate by the provincial People’s Committee.
The Xuan Thien Nghia Hung Green Steel Factory has prepared the dossier and submitted it to the Department of Agriculture and Environment for land lease appraisal. The Green Steel Factory No. 1 is awaiting approval of the feasibility report to meet the conditions for land lease application.
The investor’s representative stated that the capital for land clearance of the remaining areas within the project is ready. They also committed to prioritizing the employment of local workers in the project area.
In terms of investment progress, the Xuan Thien Nam Dinh Precast Concrete Components Factory has completed investment procedures, land handover, and obtained the land use right certificate. The project was inaugurated in November 2022 and is expected to be operational by the third quarter of 2026.
The Xuan Thien Nghia Hung Green Steel Factory has finalized approval of planning, environmental impact assessment, and infrastructure connection. It is currently perfecting the land lease dossier and is expected to commence on June 6, 2025.
The Xuan Thien Nam Dinh Green Steel Factory No. 1 has completed planning, environmental impact assessment, and agreed on power and water supply. It is currently in the process of appraising the feasibility report and finalizing the construction permit dossier.
The investor’s representative also proposed to simultaneously inaugurate the two Green Steel projects before June 17.
Concluding the meeting, the leader of the People’s Committee of Nam Dinh province requested that the relevant departments, sectors, and localities urgently complete the land lease and construction permit procedures for the projects that meet the conditions to commence before June 17.
The leader of the People’s Committee of Nam Dinh province committed to accompanying the investor in implementing and constructing the projects. At the same time, the investor was requested to closely coordinate with functional agencies and local authorities to complete the relevant procedures, ensuring the effective and safe implementation of the projects as planned.

Overview of the project area (photo taken in October 2024)
It is known that the complex of projects of Xuan Thien Group in the Green Island area has a scale of 425 hectares with a total investment of nearly VND 100,000 billion (approximately US$4 billion).
The complex includes three projects: Xuan Thien Nam Dinh Precast Concrete Components Factory, Xuan Thien Nghia Hung Green Steel Factory, and Xuan Thien Nam Dinh Green Steel Factory No. 1.
Once completed and put into operation, these projects are expected to create jobs for about 16,200 direct laborers, mainly technical workers, as well as numerous indirect jobs through the development of auxiliary services and industries.
The Northern Star: Vân Đồn’s Economic Renaissance
Once a quiet island region nestled in the Bai Tu Long Bay, Van Don is now poised for a strategic transformation. Located in the northeastern part of the country, this area is no longer just a vacation destination but is being shaped into a coastal economic zone in the north during the 2025-2030 phase.
Vlasta – Thủy Nguyên: The Ultimate Magnet for Top-Tier Agents
In the heart of the new Haiphong, Vlasta – Thuỷ Nguyên makes a spectacular entrance with a vibrant launch and an array of special offers. Unveiling an extraordinary opportunity with a grand debut, Vlasta offers a once-in-a-lifetime chance to win a European vacation worth 200 million VND, along with incredible discounts of up to 7% and an attractive interest rate support package for 24 months.
The $300 Million Airport in Vietnam’s Town: A Global Beauty That’s Been Stalled for 3 Years. When Will Construction Begin?
After 3 long years since the groundbreaking ceremony, construction on the highly anticipated airport project, with an investment of 7 trillion VND, is yet to officially commence.