The Lao Cai – Hanoi – Haiphong Railway Project is a significant transportation development project with an estimated investment of 203,000 billion VND. Spanning approximately 390 km, this railway will connect nine provinces and cities, including Haiphong, where it will cover a distance of nearly 49 km across six districts: An Lao, Kien Thuy, Duong Kinh, Do Son, Hai An, and Cat Hai.

Following the government’s directives, Haiphong city is expediting land clearance work for this national key traffic project. The city is expected to reclaim 406 hectares of land, affecting about 30 organizations and 2,786 households. Approximately 1,330 households will need to be resettled.

A glimpse of Haiphong city.

Recognizing the critical nature of land clearance, the City Party Committee established a steering committee for this task in early May 2025, headed by the City Party Committee Secretary. The Department of Agriculture and Environment was appointed as the standing agency of the steering committee.

Since May 12, the Department of Agriculture and Environment has coordinated with the six districts to demarcate and hand over the planned boundary of the project. Localities are directed to complete this task by the end of May 2025. Meanwhile, district-level People’s Committees are proactively preparing land records and land origin dossiers to expedite the process.

Currently, the districts are also identifying resettlement areas and proposing approval for the construction of these zones to the city People’s Committee. The city urges agencies, branches, and localities to strive to hand over the cleared land promptly to facilitate the investor’s implementation of the project as per the approved schedule.

Haiphong city aims to essentially complete the land clearance work by August 2025.

You may also like

“High-Speed Dreams: Reshaping Lam Dong with a Highway Resettlement Project”

Let me know if you would like me to tweak it or provide other options!

The construction of the Tan Phu – Bao Loc and Bao Loc – Lien Khuong highway road project’s resettlement areas will be undertaken this year.

Neglecting Urban Planning Leads to a Two-Decade Wait for Homeowners to Receive Their Property Papers

Introducing the Riva Park 504 Nguyen Tat Thanh, the Tien Hung residential project, and the 9B4 – 9B8 residential project in Binh Hung: once slated for resettlement purposes, these projects have since been released to the market by the developers. However, buyers are still awaiting their pink booklets, which are yet to be issued.

A Renowned County in Hai Phong Prepares to Reclaim Land from Over 1,400 Households for a Major Project Connecting to the Capital and Northern Provinces.

The Kien Thuy District authorities in Hai Phong City plan to revoke the land of 1,428 households and ten organizations to facilitate the construction of the Lao Cai – Hanoi – Hai Phong railway project.

The Breathtaking $86 Million Coastal Road: Will the Vân Phong Economic Zone Project Face Delays?

The $86 million coastal route in the Van Phong Economic Zone, Khanh Hoa Province, is facing potential delays due to challenges in land clearance. With a budget of this magnitude, it is crucial that this project stays on track and overcomes any hurdles it may face. This development is a significant investment for the region and will undoubtedly bring positive change and opportunities to the local community.

“Expediting Three Vital Transport Projects in Quang Binh: Overcoming Obstacles in Land Clearance.”

“These are three pivotal public investment projects in Quang Binh Province that are facing significant challenges with regard to land clearance and delayed disbursement progress. Vice Chairman of the Provincial People’s Committee, Phan Phong Phu, personally inspected the sites and directed relevant units to expeditiously address the obstacles to guarantee construction stays on track.”