On June 6, 2025, Nhon Trach 4 Power Plant successfully conducted its first fire and operated in a no-load mode at 3,000 rpm, a crucial technical milestone before the turbine’s test run with load. As planned, after completing the testing and technical evaluation, the plant will officially commence commercial operations in November 2025.

As of the end of June 2025, the Nhon Trach 3 and 4 complex had completed 99.7% of the overall workload. Equipment procurement and installation have been finalized. Nhon Trach 3 Power Plant, in particular, connected to the national grid on February 5, 2025, and is currently in the test run phase. Notably, in April, this unit operated stably for 30 hours at baseline capacity, generating 812 MWh of electricity, reflecting the effectiveness of the technology and the seamless coordination between the construction units and the investor. Nhon Trach 3 Power Plant is expected to commence commercial operations in mid-August 2025.

Leaders of PVPower and the Oil and Gas Association, along with other delegates, witness the moment when Nhon Trach 4 Power Plant connects to the national grid – Photo courtesy of PVN

The Nhon Trach 3 and 4 Power Plant complex project, invested by Vietnam National Oil and Gas Group (Petrovietnam) member – Vietnam Oil and Gas Power Group Joint Stock Company (PV POWER), is the first project in Vietnam to use imported liquefied natural gas (LNG) for power generation. With a total capacity of nearly 1,500 MW, the two plants will not only contribute to the national power system amid rising loads but also pave the way for the energy industry’s new development direction, in line with the government-approved Power Development Plan VIII’s orientation for LNG power development.

You may also like

The Power of Words: Crafting Captivating Copy for Web Success

Unleashing the Potential of Nhơn Trạch 4 Power Plant: Synchronizing with the National Grid

On June 27th, at 1:55 p.m., the Nhon Trach 4 Power Plant, one of the first LNG-fired power plants in Vietnam, successfully synchronized with the national grid, initially delivering an impressive 50 MW of power. This significant milestone, a first for the power plant, marks a crucial step in the testing phase before commencing commercial operations.

The Billion-Dollar Project Lights Up: A Historic Turning Point for the Energy Sector

This is one of the nation’s key LNG-to-power projects. A significant initiative, it is set to make a substantial impact on the country’s energy landscape.

The First Metro Line: Full-Throttle Trial Run

The upcoming trial run of Metro Line 1 at full capacity marks a pivotal step towards its highly anticipated commercial operation later this year.