The Quiet Coastal Projects: Unlocking Development in Quang Nam

The stagnant state of coastal projects can be attributed to three key issues, as identified by the Management Board of Quang Nam Province's Department of Planning and Investment. These issues revolve around enterprises' security deposit requirements, challenges in land clearance compensation, and financial constraints.

0
52

Mr. Ho Quang Buu, Vice Chairman of the People’s Committee of Quang Nam Province, chaired the press conference. Photo: Hoai Van

At the press conference on the socio-economic situation in the first six months and key tasks for the coming period, held on the afternoon of July 9th, several pressing issues were raised by journalists, including the slow progress and abandonment of coastal tourism projects, the rearrangement and placement of officials after the merger of administrative units, and the restoration of state capital in the Quang Nam Water Supply and Sewerage JSC.

Quang Nam held a press conference on socio-economic situation in the first six months and key tasks for the last six months.

According to the report, in the first half of the year, the GRDP growth rate increased by 2.7%; industrial production has recovered, trade and service activities have been vibrant, international visitors have increased significantly, and agricultural production has ensured progress and comprehensive growth.

Revenue and expenditure of the state budget were guaranteed according to the estimate (total state budget revenue in the first six months was VND 12,221 billion, reaching 51.8%); import and export value maintained a fairly high increase, and domestic and foreign investment attraction increased strongly in both the number of projects and registered capital.

However, there are still some shortcomings and limitations, such as the economy has not really recovered, especially in industrial production; some sources of revenue are low; disbursement of public investment capital is slow; compensation, site clearance, and handover of land faces many obstacles.

Businesses still face difficulties, with the number of businesses withdrawing from the market exceeding the number of newly established enterprises. The progress of key projects and works has not ensured timely implementation; complaints and denunciations related to land issues are complex and prolonged in some localities.

Mr. Nguyen Hung answered questions about the stagnant situation of billion-dollar coastal tourism projects in Quang Nam.

At the press conference, a journalist from Tien Phong Newspaper asked about the causes and solutions to the stagnant situation of billion-dollar coastal tourism projects in Quang Nam Province.

Mr. Nguyen Hung, Deputy Director of the Department of Planning and Investment of Quang Nam Province, said that currently, the total number of tourism projects along the coast is 58, of which 5 have been revoked, leaving 53 projects that are still valid and continue to be implemented.

25 out of the 53 projects have been put into operation, contributing to the provincial budget. The remaining projects are under development, and some of them are facing difficulties and obstacles.

According to Mr. Hung, there are three main groups of obstacles faced by investors: deposit for business guarantee as required by regulations; adjustment of general planning; and difficulties in capital sources.

Many enterprises are struggling with the requirement to deposit a business guarantee. For commercial and service projects with a scale of about VND 3,000-4,000 billion, the deposit amount is very large. In this regard, the Department has advised and requested enterprises to commit that if they do not provide a guarantee within a certain period after being granted a certificate of investment policy decision adjustment, their project will be revoked.

For the group of projects facing difficulties due to site clearance and compensation, it is proposed to review and adjust the areas where compensation cannot be implemented. These areas will be handed over to the locality for management to ensure construction connectivity with the region’s infrastructure. For projects with feasible compensation plans, local units are requested to continue with the implementation.

“Although various solutions have been proposed, if investors are unable to implement them due to compensation issues or lack of financial capacity, the projects will be resolutely revoked,” said Mr. Hung.

You may also like

Conclusion of the Inspection at the Testing Center in Hoi An

Through its inspection, the Quang Nam provincial inspectorate has identified several violations in the process of investing in the construction of the Motor Vehicle Registration Center in Hoi An City.

Special Opportunities Unfolding in Vietnam’s Economy

CEO of Citi Vietnam: “Every country has its own destiny and always has special opportunities opening up. Vietnam is currently experiencing this.”

Trade and Commerce industry strives to overcome challenges and create stronger transformations in 2024.

On the occasion of the new Lunar Year – Year of the Tiger, a reporter from Tin Tuc News had an interview with the Minister of Industry and Trade, Nguyen Hong Dien, to discuss the achievements of 2023 and the specific tasks for the sector in 2024.

Optimistic Signals from Vietnam’s Economy in the New Year

The State budget revenue has achieved positive results, with strong growth in retail sales of goods and revenue from consumer services, attracting foreign direct investment with good results, and witnessing significant changes in disbursement of public investment capital. These are optimistic signals for a prosperous year 2024 for the Vietnamese economy.