The Long Thanh International Airport Passenger Terminal: An Architectural Marvel Unveiled

The steel structure for the airport terminal roof is valued at approximately 3,500 billion VND, weighing in at 36,000 tons. This critical component represents a significant 10% of the total contract value for the Long Thanh International Airport passenger terminal project.

0
45

As of August 27th, Mr. Duong Quang Dien, Deputy Director of the Long Thanh Airport Project Management Board, shared that the construction consortium has commenced the installation of the steel structure for the airport’s passenger terminal roof. The installation is expected to be completed by mid-2025.

According to the Long Thanh Airport Project Management Board, four major packages are currently underway: the passenger terminal, the runway, two connecting transport routes, and the air traffic control tower.

The passenger terminal is considered the “heart” of Phase 1 of the Long Thanh Airport. According to ACV, Phase 1 of the airport is expected to be completed and operationally tested before August 31, 2026. On September 2, 2026, the airport will welcome its first commercial flight.

Regarding the runway, the construction consortium has mobilized thousands of workers and machinery to work on dozens of construction sites with the determination to complete and put the runway into operation before April 30, 2025.

For the two connecting transport routes (T1 and T2), more than 50% of the work has been completed so far, and the routes are expected to be open to traffic by the end of 2025.

Concerning the air traffic control tower, the concrete work will be finished by September 2024, after which the steel structure and equipment installation will commence. Upon completion, the total height of the tower will be 123 meters. The teams are striving to substantially finish the tower by April 30, 2025, to facilitate calibration flights.

The steel structure for the passenger terminal roof is valued at approximately VND 3,500 billion, accounting for about 10% of the contract value of the terminal construction project.

The quantity of steel structures for the terminal roof installation is approximately 36,000 tons. The steel materials for the roof installation are imported from abroad and processed domestically.

To facilitate the steel structure installation, the contractor has mobilized specialized machinery and equipment to the construction site.

The steel structure installation for the Long Thanh Airport passenger terminal roof is about one month ahead of the approved schedule.

The installation started with the wings, followed by the main body of the terminal. Prior to the steel roof installation, the quality of the steel was thoroughly inspected, and experiments were conducted according to the project’s technical standards to ensure quality.

The passenger terminal is the most critical component of the Long Thanh Airport Project. To date, the construction consortium has substantially completed the flooring of the four stories and has begun interior finishing. The terminal’s finishing process involves numerous steps.

The steel roof of the Long Thanh Airport passenger terminal is taking shape.

You may also like

High-speed Fever from Bien Hoa to Vung Tau through Dong Nai Province

After 7 months of construction, the Biên Hòa-Dồng Nai expressway project is still facing challenges with land clearance.

The Power of Lizen: Consistently Winning Massive Bids

Lizen has achieved a significant milestone by successfully deploying and implementing major high-speed construction projects in 2023. The company’s revenue has reached 2,030.5 billion VND, which is twice the amount compared to 2022. However, the post-tax profit has reached its lowest point in the past 6 years, dropping down to only 118.3 billion VND.

Top Travel Destination in Southeast Asia: Long Thanh Airport Tour Package

To leverage the advantages of Long Thanh International Airport, Dong Nai province has proposed the development of high-end shopping complexes around the airport to cater to the consumption needs of the middle class and affluent.

“Conquer the Sunshine, Defeat the Rain”: Completing the 500 kV Circuit 3 Line by June 2024, All throughout Tet”

On the afternoon of January 27th, Prime Minister Pham Minh Chinh visited four provinces, namely Thai Binh, Nam Dinh, Ninh Binh, and Thanh Hoa, to inspect the construction and provide encouragement to the construction forces of the 500 kV Transmission Line Project, Circuit 3, from Quang Trach (Quang Binh province) to Pho Noi (Hung Yen province) by handing out gifts.