Determination to Complete Land Clearance for the Tam Trinh Road Construction Project by the End of September 2024

Under the direction of the Hoang Mai District Party Committee, the site clearance and compensation for the Tam Trinh Road construction project is expected to be completed by October 1, 2024. The relevant agencies and units are diligently working together to implement effective solutions and encourage local residents to cooperate and hand over the required land area for the project's success.

0
32

The Tam Trinh Road construction project was approved for investment by the Hanoi People’s Committee in 2012. The 3.5km road, connecting Minh Khai Street to Ring Road 3, was estimated to cost VND 2,066 billion.

According to the Hoang Mai District People’s Committee, the project commenced in 2016 and was expected to be completed within three years. However, various challenges halted construction, and in December 2023, the Hanoi People’s Committee issued a decision to adjust the project, increasing the investment capital to VND 3,354 billion. The implementation period was also extended to span from 2016 to 2026, a seven-year delay from the initial plan.

Tam Trinh Road in Hoang Mai District

Following the project adjustment, the Hoang Mai District Project Management Unit, the District Land Development Center, and three wards (Hoang Van Thu, Mai Dong, and Tam Trinh) intensified their focus on land clearance.

Mr. Do Minh Tam, Chairman of the Tam Trinh Ward People’s Committee, shared that the project route covers 1.3 km in the ward, affecting nearly 1,300 cases of land clearance. Of these, 800 cases involve agricultural land, and the rest is residential. “The west side of Tam Trinh has completed land clearance, while the east side, concerning 201 households, has 146 households yet to agree on compensation,” Mr. Tam said.

Despite the challenges, Mr. Tam assured that they are determined to meet the target set by the Hoang Mai District Party Committee to complete land clearance by October 1, 2024. They are employing various solutions, focusing on propaganda and encouraging project-affected residents to hand over their land. Additionally, with the Land Law of 2023 in effect, a council must be established to determine the initial land registration, including land use purposes, duration, and other factors.

“The households have requested the city to apply a uniform compensation policy for the project. While the route passes through different wards, the compensation rates vary, causing dissatisfaction among residents,” Mr. Tam explained.

Mr. Tam also mentioned that the ward is simultaneously working on land clearance for five other projects. As a result, district officials are working tirelessly, even on holidays and after hours, to propagate and motivate residents to hand over their land for the projects.

The Hoang Mai District People’s Committee has issued land recovery notices to 146 households for this project. They have also conducted surveys, measurements, and approved 186 plans in Mai Dong Ward, demolished ten structures and Mai Dong market stalls, confirmed land origins for 49 households, and drafted 107 plans in Hoang Van Thu Ward. As per the Hoang Mai District Party Committee’s directive, land clearance must be completed by October 1, 2024.

You may also like

The Capital’s Renowned Late-Night Pho Spots Still Buzzing During Holidays

For a satisfying end to your late-night National Day celebrations, head to Hanoi’s renowned pho restaurants to satiate your hunger and rejuvenate your weary soul.

“Huge Disparity in Thu Duc City’s Land Prices: Official Resettlement Land Price Reaches 51 Million VND per square meter, While the Standard Land Price is Only 1.5 Million VND.”

In the latest development regarding adjustments to the current land price framework, the Ho Chi Minh City Department of Natural Resources and Environment has submitted a report to the Ministry of Natural Resources and Environment.

The Ultimate Residential Project: Unveiling the Truth Behind the Crumbling Roads

The residential construction project in Long Bien Ward, Long Bien District, Hanoi, has caused significant damage to the Co Linh road. The project developer has been fined VND 180 million for their negligence, with authorities taking a firm stance to ensure the safety and integrity of the district’s infrastructure.

The Master Manipulator: How a Former CEO Allegedly Caused Losses of Over $6 Million

The prosecution asserted that defendant Nguyen Thi Loan, the former chairman of Vimedimex, directed and utilized three companies under her control to participate in auctions, bidding in rounds to win a plot of land, which resulted in financial loss to the state.

High-Speed Handover: TP HCM – Moc Bai Expressway from April 2025

The estimated cost for compensation, support, and resettlement for the project’s Component 3, which covers the city, is 7,102 billion VND, an increase of 1,832 billion VND from the previous figure. This significant rise in expenditure underscores the project’s complexity and scope, requiring meticulous planning and execution to ensure a successful and seamless transition for those affected.