The $21 Million Bridge Connecting Binh Duong and Dong Nai Provinces: A First Look Before Its Grand Opening

The Bach Dang Bridge is a pivotal infrastructure project, seamlessly connecting localities in the South-East region and the dynamic economic hub of Southern Vietnam. This strategic connector facilitates smoother travel and trade, fostering growth and prosperity for the entire region.

0
68

The Bach Dang 2 Bridge, connecting Binh Duong and Dong Nai provinces, is set to open to traffic this National Day holiday after nearly three years of construction.

Workers are seen blowing dust off the bridge, installing handrails, lighting systems, drainage systems, and the remaining approach road.

Nearly three years in the making, the Bach Dang 2 Bridge project has reached approximately 99% completion. Despite challenges with land clearance and the COVID-19 pandemic, contractors, engineers, and workers have strived to complete the project ahead of schedule.

The Bach Dang 2 Bridge project, with a total investment of nearly VND 500 billion, commenced construction in late 2021. The entire project spans nearly 3 kilometers, including a 400-meter-long bridge and a 17-meter-wide four-lane road, along with approach roads on both ends.

Workers are in the final stages of construction to ensure the bridge opens to traffic on the National Day holiday.

The remaining work includes installing lighting poles and handrails to complete the project as scheduled.

The contractor is currently working on the approach road to the bridge.

Upon its completion, the bridge will play a crucial role in connecting provinces and cities in the Southeast region, particularly the key economic zone in the South.

You may also like

Celebrating 79 Years of Independence: Nurturing the Strong Bonds of Friendship Between Vietnam and its Allies

Over the past few days, the Embassy of Vietnam in many countries celebrated the 79th National Day of the Socialist Republic of Vietnam (September 2, 1945 – September 2, 2024).

The Reason Thousands of Students Haven’t Received Their Licenses After Testing in Binh Duong.

“The delay in issuing driver’s licenses to successful examinees in Binh Duong Province has been attributed to a shortage of printing paper and supplementary materials, according to the Provincial Department of Transportation. The department is currently in the process of identifying a suitable tenderer to address this issue.”

What Are the 8 Land Plots Up for Auction, Expected to Bring in $297 Million for Binh Duong Province?

In 2024, Binh Duong province plans to auction eight public land plots spanning 284 hectares, aiming to generate VND 6.7 trillion.

A Real Estate Firm Seeks to Raise $150 Million in Private Placement to Repay Bond Debt, Stock Plunges as Buyers Vanish

This real estate enterprise seeks shareholder approval for a private placement of 35 million shares, with a minimum offering price of 10,000 VND per share.

The Race to Meet the Deadline: Investors’ Response to the Long Thanh Airport Project

The efforts to bring Long Thanh Airport in Dong Nai Province on track, coupled with the development of key transportation projects such as roads 25B, 25C, 769, 770B, and 773, the Bien Hoa-Vung Tau expressway, and Ho Chi Minh City’s Ring Road 3, are sending positive signals to the real estate market.