The Coastal Highway and Thuan An Sea Gate Bridge project in Thua Thien-Hue province is a significant infrastructure development with a total length of 7.785 km, including a 2.36 km-long bridge. The remaining section consists of access roads connecting National Highways 49A and 49B.
With an investment of VND 2,400 billion, the project is being developed by the Thua Thien-Hue Province Traffic Construction Investment Project Management Authority. It is expected to be completed by March 2025.
Currently, construction is focused on the Thuan An Sea Gate Bridge, which will have a width of 20 meters, while the main bridge span, from pillar 25 to pillar 28, will be 23.5 meters wide.
Despite the scorching weather during the National Day holiday on September 2nd, the contractors continued to work on the project, keeping the construction site bustling with activity.
The project commenced in March 2022, with a joint venture of Tan Nam Construction Joint Stock Company, Dat Phuong Joint Stock Group, and 479 Hoa Binh Joint Stock Company as the contractors, with a contract value of over VND 2,000 billion. So far, approximately VND 1,400 billion, or 68.9%, has been executed.
The contractors are diligently working on the construction of 50 bridge pillars, beam launching, and completing the segmental box girder construction, concrete pouring for the bridge deck, and installation of bridge railings. The form of the largest sea-crossing bridge in Central Vietnam is gradually taking shape.
According to the Thua Thien-Hue Province Traffic Construction Investment Project Management Authority, Tan Nam Construction Joint Stock Company and Dat Phuong Joint Stock Group are responsible for constructing the central pillars from T26 to T28 of the Thuan An Sea Gate Bridge, with a total length of 458 meters, utilizing the Extradosed and cable-stayed methods.
These units are making concerted efforts, with Tan Nam Construction Joint Stock Company having cast 46 meters of the bridge span at pillar T26, and Dat Phuong Joint Stock Group having cast 44 meters and tensioned 6 out of 34 cables. “The bridge span construction method involves direct reinforced concrete pouring, with each pour creating a 4-meter-long segment, and it takes us about 10 days to complete one such segment,” said the investor’s representative.
Mr. Nguyen Van Cuong, Deputy Director of the Thua Thien-Hue Province Traffic Construction Investment Project Management Authority, shared that according to the construction schedule, the Thuan An Sea Gate Bridge is expected to be technically opened to traffic in early 2025. “However, the province recently requested accelerating the construction to achieve technical opening in October 2024, but due to technical factors, this target could not be met. The units are focusing on construction to strive for technical opening by the end of this year,” Mr. Cuong informed.
According to the investor, the scope of site clearance for phase 1 in Hai Duong and Thuan An wards involves a total land area of over 31.7 hectares, including 900 tombs and 120 households requiring resettlement. So far, Hai Duong ward has basically completed site clearance and handed over the area to the construction unit.
In Thuan An ward, 15 households have not yet relocated their tombs due to land search or personal matters. Out of 54 cases approved for compensation to construct the bridge abutments, 32 households have handed over the land, but due to the lack of access roads, only demolition has been carried out without construction initiation.
When Will the Highway Connecting Binh Duong and Dong Nai Provinces Open?
As of now, the Bach Dang 2 Bridge project, spanning the Dong Nai River and connecting Binh Duong and Dong Nai provinces, is nearing completion. The construction team is working diligently to finalize the remaining stages of the project. The bridge is set to be fully completed before September 20th and will be open for traffic on the day of the announcement of the Binh Duong provincial planning.
The Masterful Don Hunters of the Tra Khuc River
The 130-kilometer-long journey of the Tra Khuc River through the province of Quang Ngai is a testament to its resilience as it cascades over numerous rapids and waterfalls before finally merging with the vast sea at Cua Dai. This unique confluence of freshwater and seawater has given birth to a truly extraordinary and singular mollusc, the ‘don’, which cannot be found in any other Central Vietnamese river.