With the dry season setting in, contractors have mobilized additional machinery and personnel to accelerate construction.
![](https://cafefcdn.com/203337114487263232/2024/12/5/c2-1733361135312-1733361135395982876818.jpg)
Over 500 workers and 410 pieces of equipment are simultaneously constructing the 48km-long Khanh Hoa – Buon Ma Thuot expressway section in Dak Lak province.
![](https://cafefcdn.com/203337114487263232/2024/12/5/c3-1733361136497-17333611367611674210550.jpg)
To ensure timely completion, construction is taking place in three shifts, with four teams working continuously through the day and night.
![](https://cafefcdn.com/203337114487263232/2024/12/5/c4-1733361137556-17333611378801544773560.jpg)
The contract, which involves challenging mountainous terrain, is entering its final phase.
![](https://cafefcdn.com/203337114487263232/2024/12/5/c5-1733361138726-1733361138873415094829.jpg)
The Phoenix Pass tunnel is taking shape.
![](https://cafefcdn.com/203337114487263232/2024/12/5/c6-1733361139648-17333611398771457230680.jpg)
Contractors are accelerating their efforts to “carve through the mountains.”
![](https://cafefcdn.com/203337114487263232/2024/12/5/c7-1733361141051-17333611411781849982623.jpg)
Several sections of the route have already received cement-reinforced base layers. The road surface is expected to be laid as early as this December.
![](https://cafefcdn.com/203337114487263232/2024/12/5/c8-1733361142491-1733361142657164437904.jpg)
Land clearance for the third component project of the Khanh Hoa – Buon Ma Thuot expressway has reached 98.6%. Local authorities in Dak Lak are working diligently to hand over the remaining land to the contractors.
![](https://cafefcdn.com/203337114487263232/2024/12/5/c9-1733361143693-17333611438251579907179.jpg)
Challenges related to material sources, such as soil, stone, and waste disposal sites, have been reported and are being urgently addressed by the provincial government to expedite the project’s progress.
![](https://cafefcdn.com/203337114487263232/2024/12/5/c10-1733361144926-1733361145364723392260.jpg)
The investors and contractors of the third component project of the Khanh Hoa – Buon Ma Thuot expressway are determined to complete the project by August 30, 2025.
The Prime Minister’s Fifth Inspection of the Long Thanh Airport Project Site
On December 3rd, Prime Minister Pham Minh Chinh visited Dong Nai to inspect the progress of two key infrastructure projects: the Long Thanh International Airport and the Bien Hoa-Vung Tau Expressway. With a keen eye for detail, the Prime Minister assessed the development of these projects, which are expected to boost economic growth and connectivity in the region.
No Delays for the Expressways in the Mekong Delta Due to Sand and Stone Shortages
Deputy Prime Minister Tran Hong Ha has instructed the Ministry of Transport, relevant agencies, and contractors to proactively coordinate with local authorities to expedite the supply of fill materials. He emphasized that there should be no delays in the construction of expressways in the Mekong Delta region due to a shortage of sand and rocks.