Mr. Duong Duc Tuan, Vice Chairman of the Hanoi People’s Committee, made this directive during a visit to offer Lunar New Year greetings to the officers and workers of the construction site of Component Project 2.1 (Ring Road 4 – Capital Region Project) on the morning of January 24th.
Regarding the project’s progress, Mr. Nguyen Hoang Hai, Commander of Package 9, the contractor of Vietnam Construction and Import-Export Joint Stock Corporation (Vinaconex), shared that Component 2.1 was commenced on June 25, 2023.
Hanoi Vice Chairman Duong Duc Tuan and the delegation inspecting the progress of Component Project 2.1 on January 24th.
Up to now, the contractors have achieved over 50% of the contract value. Specifically, sand filling for the road foundation stands at 85%, while earth filling accounts for approximately 62.27%, and crushed stone filling reaches around 35%. The construction of bridges and culverts is also being carried out simultaneously by the contractor. As of now, the site clearance work has been completed for over 98.4% of the total area, with only about 13 hectares left to be handed over.
Notably, in the districts of Me Linh, Dan Phuong, and Hoai Duc, the contractor has laid 15 out of 31 kilometers of asphalt concrete.
Workers at the construction site of Component Project 2.1
According to Mr. Hai, the project will continue until January 25th and then pause for the Lunar New Year holiday. The contractors will resume work on the 6th day of the new year.
Representatives of the contractors pledged that immediately after the holiday, they would work in three shifts and four crews to ensure the completion of the parallel road by the end of 2025.
At the meeting, Vice Chairman of the Hanoi People’s Committee, Duong Duc Tuan, highly appreciated the efforts of the contractors in the past time. So far, they have achieved about 50% of the contract value and 10% of the 2025 plan.
Mr. Duong Duc Tuan, Vice Chairman of Hanoi, requested that the units exert more considerable efforts in implementing the remaining road and bridge items, striving to open the parallel road of Ring Road 4 by the end of 2025.