On September 14, the joint contractors for Package 4.6, responsible for constructing Runway 1, taxiways, and the apron at Long Thanh International Airport, are expediting the reinstallation of approach lights and runway edge lights on Runway 1. This effort aims to support the upcoming calibration flights at the airport.
Completion of signal light installation on Runway 1 at Long Thanh Airport to facilitate calibration flights.
|
Specifically, starting September 26, the Vietnam Aviation Authority will collaborate with relevant units to commence inspection and calibration flights at Long Thanh Airport. These flights, conducted over more than 10 days using a Beechcraft B300 aircraft, will take place during late-night or early-morning hours to minimize disruption to commercial operations at Tan Son Nhat Airport.
Runway 1 at Long Thanh Airport spans 4 kilometers in length and 70 meters in width, capable of accommodating the most advanced aircraft currently in operation. Package 4.6, initiated by the joint contractors in August 2023, was originally slated for completion by July 2025, with a 23-month construction timeline. However, the schedule was later adjusted, advancing the completion date to April 2025, three months ahead of the original plan.
The signal lighting system on Runway 1 at Long Thanh Airport was fully installed and successfully tested in April 2025, officially illuminating the runway.
|
To date, Package 4.6 has achieved over 95% completion, with Runway 1 nearly finished. The remaining work, located in areas awaiting settlement and intersecting with ongoing underground infrastructure packages at the cargo apron, will be completed in the coming period.
By late April 2025, the signal lighting system on Runway 1 had been fully installed and successfully tested, officially illuminating the runway. Subsequently, during the construction of other components of the Long Thanh Airport project, some lights were temporarily removed to facilitate the movement of construction vehicles and machinery across Runway 1. These lights are now being reinstalled by the contractors to support the upcoming calibration flights.
Nguyễn Tuấn
– 09:26 14/09/2025
A Landmark Achievement: Long Thanh Airport’s Journey to a Safe and Timely Completion
On September 7, Deputy Prime Minister Tran Hong Ha, head of the task force for the Long Thanh International Airport project, inspected the construction progress on-site and worked with the Ministry of Construction, the Vietnam Airports Corporation (ACV), contractors, and relevant ministries and sectors.
“Brand Finance: Vinamilk Soars to Lead in Global Dairy Brand Potential”
Vinamilk has been recognized as the world’s most promising dairy brand by Brand Finance, surpassing numerous international giants. With a Brand Strength Index rating of AAA, the highest possible rank, Vinamilk has achieved a remarkable feat. But what has fueled this brand’s extraordinary success and global recognition?
Transferring All International Flights to Long Thanh: A Daunting Task for the Long Thanh- Dau Giay Expressway
The delays and lack of synchronization in the infrastructure connectivity system have raised concerns among the public about reduced investment efficiency and a negative impact on passenger experience.