The Vietnam General Confederation of Labor and Vietnam Electricity (EVN) have prioritized this project as an urgent focus, aiming for its completion and power supply by 2025.
EVNNPT serves as the project investor, with the Central Power Projects Management Board overseeing its management and execution. Power Transmission Company 1 will take over operations upon completion.
The 220kV Vung Ang Substation is located in Trai hamlet, Vung Ang ward, Ha Tinh province. By 2030, it’s planned to accommodate 2 transformers with a capacity of 2x250MVA, starting with 1 transformer of 125MVA. The station is designed with three voltage levels: 220kV, 110kV, and 22kV.
Stakeholders witness the power supply commencement of the 220kV Vung Ang Substation and its connection project.
The connecting line spans 2×13.4 km, traversing Vung Ang and Song Tri wards in Ha Tinh province.
Construction faced significant challenges, particularly in land clearance and compensation, especially in the Tay Yen residential area of Vung Ang ward.
Under EVNNPT’s decisive leadership, with support from Ha Tinh Provincial People’s Committee, Ha Tinh Police, and local authorities, along with timely union encouragement, the 220kV Vung Ang Substation began operations on September 21, 2025.
Overview of the 220kV Vung Ang Substation and its connecting line.
To maximize project efficiency, the 220kV connecting line must be completed promptly. Construction faced resistance from some residents who obstructed wire installation between poles 06-08, a 600-meter stretch.
With Ha Tinh Provincial Party Committee and People’s Committee’s guidance, and support from local authorities and police, security forces were deployed to ensure construction, demonstrating the province’s commitment to this key project.
EVNNPT Union leaders encourage workers during the connecting line construction on October 21, 2025.
The 220kV Vung Ang Substation and its connection project are vital for powering critical loads in Ha Tinh, especially the Vung Ang Economic Zone, home to key industrial parks and factories. It also frees up capacity for Vung Ang Thermal Power Plant, reduces energy losses, ensures grid safety, and enhances power reliability, supporting socio-economic and political development in Ha Tinh.
The 220kV connecting line from the 220kV Vung Ang Substation to Vung Ang Thermal Power Plant.
Completing this project is a meaningful contribution by EVNNPT and CPMB employees to the 11th National Emulation Congress of Vietnamese Workers and Labor Unions in 2025, organized by the Vietnam General Confederation of Labor in Hanoi.
Completion of the 220 kV Vũng Áng Substation Project and Grid Connection
On October 25th, the National Power Transmission Corporation (EVNNPT) and the Central Power Project Management Board (CPMB), in collaboration with relevant units, successfully energized the 220 kV transmission line connection, marking the full completion of the Vung Ang 220 kV Substation and its associated transmission line project.
Accelerating Progress: EVNNPT Speeds Up the 500kV Hai Phong – Thai Binh Power Line Project
On October 8, 2025, Mr. Phạm Lê Phú, General Director of the National Power Transmission Corporation (EVNNPT), led a working delegation to inspect the progress and urge the construction of the 500kV Hải Phòng – Thái Bình power line project.