The Ho Chi Minh City Ring Road 3, passing through the former Binh Duong province, is taking shape as two overpasses have been successfully connected. This section boasts an investment of nearly 1.9 trillion VND.

0
21

On January 9th, as reported by Tien Phong Newspaper, the Ho Chi Minh City Ring Road 3 project, specifically the section passing through the former Binh Duong province, has gradually taken shape following the completion of two overpass connections.

Package XL3, spanning from Binh Chuan Intersection to Binh Goi Bridge over the Saigon River, is part of Component Project 5 of Ho Chi Minh City’s Ring Road 3, traversing the former Binh Duong province.

Package XL3 runs through the wards of Thuan Giao, Phu Loi, Thu Dau Mot, and Thuan An.

The section from Binh Chuan Intersection to Binh Goi Bridge spans approximately 10 kilometers, with a total investment of around 1,852 billion VND.

Phase 1 of the section from Binh Chuan Intersection to Binh Goi Bridge includes the construction of a 4-lane expressway with a design speed of 100 km/h, along with parallel roads connecting to the existing transportation network.

Construction began in late 2023, and the overpass across National Highway 13 and Cach Mang Thang Tam Street has now been connected.

This is the overpass of Ho Chi Minh City’s Ring Road 3 crossing Cach Mang Thang Tam Street.

The overpass across Cach Mang Thang Tam Street is undergoing final touches after the connection.

Ho Chi Minh City’s Ring Road 3 extends from National Highway 13 through Cach Mang Thang Tam Street to the Saigon River.

Cach Mang Thang Tam Street runs through a densely populated urban area.

This is Cach Mang Thang Tam Street.

You may also like

Exclusive Preview: The Mega Interchange Connecting Three Highways Through Ho Chi Minh City Ahead of Technical Opening

The Mỹ Yên Interchange, connecting the Ho Chi Minh City – Trung Lương Expressway, Bến Lức – Long Thành Expressway, and Ho Chi Minh City’s Ring Road 3, is set to open for technical traffic on December 19th. This development significantly enhances connectivity at the western gateway of the city.

Which Route Connecting Long Thanh Airport is About to Open?

The Biên Hòa – Vũng Tàu Expressway, the section of Ring Road 3 in Ho Chi Minh City passing through Đồng Nai Province, and roads T1 and T2—all critical transportation projects linking Long Thành Airport—will officially open for technical inspection on December 19th.

Aerial View of Ho Chi Minh City’s Ring Road 3 Through Urban Areas Ahead of Official Opening

With just over two weeks until the deadline, the 14.7 km elevated section of the HCMC Ring Road 3 is accelerating construction, focusing on completing critical packages to ensure operation by December 19.

New Milestone Achieved on Ho Chi Minh City’s Ring Road 3

With 66.3 km slated for technical completion by December 19, the Ho Chi Minh City Ring Road 3 project is poised to reach its finish line in record time.

First Stretch of Ring Road 3 Nears Completion, Set to Open Soon

Deputy Prime Minister Mai Văn Chính inspected the progress of the Ring Road 3 project, urging local authorities to accelerate construction to meet the technical completion deadline for the road’s opening.