Long Thanh International Airport Project is a key national infrastructure project with a total investment of approximately $16 billion. Once completed, it will become Vietnam’s largest airport. The Vietnam Airports Corporation (ACV), one of the project’s key executors, envisions Long Thanh as a major regional transit hub, competing with leading airports like Singapore’s Changi and Thailand’s Suvarnabhumi.
Currently, Phase 1 is underway, comprising four key components. According to the Ministry of Construction, construction progress aligns closely with the plan, ensuring completion and operation by June 2026.
Installation of the steel pipe bridge at Long Thanh Airport’s passenger terminal. Photo: DNCC
For Component 1, all six government agency headquarters are now complete. The Customs Department (Ministry of Finance) has finalized construction and obtained fire safety and completion approvals. The remaining five buildings are undergoing final inspections, scheduled for completion in January and February 2026.
Component 2’s air traffic management facilities, including the control tower, technical building, VIP lounge, and power house, were completed by December 19, 2025. Contractors are now installing electrical systems, fire safety measures, and tunnel cabling, expected to finish by February 2026.
Essential air traffic systems (primary/secondary radars, radio stations, and meteorological equipment) are nearly installed. Trial operations are set for April 2026, with VATM overseeing final preparations.
The Ministry of Construction urges VATM to expedite tunnel cabling and system integration to meet the June 2026 commercial launch deadline.
Long Thanh Airport construction site. Photo: Government News
Component 3, the most critical part of Phase 1, has completed 3 out of 15 packages. The Ministry of Construction confirms 10 remaining packages are on track for June 2026. ACV is accelerating work on key packages (4.8, internal transport; 5.10, passenger terminal) by deploying additional labor and equipment.
During a January inspection, ACV Deputy Director Nguyen Tien Viet stated, “All packages are under simultaneous construction with 15,000 workers and 3,000 machines. Our goal is commercial operation by June 2026.”
Component 4’s support facilities, including catering services and maintenance hangars, are progressing on schedule for June 2026 completion.
Weighing Vietnam’s Future Aviation Giants: The Southern International Gateway vs. The Northern Airport Redefined
Nestled beyond the urban core, both airports share a similar scale, handling tens of millions of passengers annually. Yet, their spatial development paths diverge strikingly.
Prime Location Near Long Thanh Airport: Over 3,000 Affordable Social Housing Units Starting at 450 Million VND in Dong Nai’s Golden Zone
Two groundbreaking social housing projects in Dong Nai, with a combined investment of over 2.3 trillion VND, are set to transform the region’s affordable housing landscape. Scheduled for completion by Q1 2028, these developments promise to address critical housing needs while fostering sustainable community growth.
SJ Group Accelerates Vista Nam An Khanh Project Deployment as Scheduled
After more than a month since signing the construction contract with Viettel Construction and Vinaconex1, the Vista Nam An Khánh site is witnessing significant progress. Construction is accelerating, with work organized in structured phases, and multiple components are being executed simultaneously as per the planned schedule.



















