The Fourth Visit to the $16 Billion Mega-Project with 6,000 Workers: The Prime Minister’s Crucial Directive

Prime Minister demands an expedited timeline, aiming for substantial completion of this monumental project by December 31, 2025.

0
41

Target Completion Date: December 31, 2025

On September 24, during his working visit to Dong Nai province, Prime Minister Pham Minh Chinh inspected the progress of two key transport infrastructure projects in the area: the Long Thanh International Airport and the Bien Hoa-Vung Tau Expressway.

This was the fourth time in over two years that the Prime Minister has inspected and urged progress on the Long Thanh International Airport project, demonstrating the Party and State’s special attention to this endeavor.

The Long Thanh International Airport project is the largest airport project in Vietnam to date and is of particular importance to the socio-economic development of the Southeast region and the country as a whole.

Since the Prime Minister’s last visit to the site in February 2024, significant progress has been made across various components and structures in just seven months.

Prime Minister Pham Minh Chinh at the construction site of the Long Thanh Airport Phase 1 – Photo: VGP/Nhat Bac

Notably, Component 2 – the Air Traffic Control Tower, is two months ahead of schedule, and Component 3 – the Passenger Terminal, has completed 100% of the foundation work, 20 days ahead of schedule for the structural framework, and 10 days ahead of the overall schedule. The runway has also substantially completed its foundation work, three months ahead of the contract schedule.

During the meeting at the construction site, Prime Minister Pham Minh Chinh emphasized that this project is a symbol of the XIII Congress of the Party. Therefore, the Prime Minister requested shortening the timeline compared to the previous plan, aiming to substantially complete this symbolic project by December 31, 2025, to commemorate the XIV Congress of the Party, the 80th anniversary of National Day, and the 50th anniversary of the liberation of the South and national reunification.

“We have sufficient grounds to shorten the timeline and substantially complete the project by December 31, 2025, as we have gained more maturity and experience in implementing large-scale infrastructure projects, with most procedures already completed. Moreover, land clearance is almost finished, and we have adequate human resources and machinery at the construction site,” quoted the Government Portal from the Prime Minister’s directive.

A bird’s-eye view of the “super airport,” the largest in the country, taking shape – Photo: ACV

Consideration of a Railway or Subway Connection to the Airport

Notably, during the meeting on September 24, Prime Minister Pham Minh Chinh instructed the Ministry of Transport to promptly report to the authorized agency the proposal for the second runway. Deputy Prime Minister Le Thanh Long was assigned to directly oversee the submission of this proposal to be included in the agenda of the 8th session of the XV National Assembly.

Additionally, the Head of the Government assigned the Ministry of Transport and relevant agencies to promptly study and implement connectivity solutions for the Long Thanh Airport (including options for railways, subways, etc.).

Furthermore, relevant units were instructed to follow the Government’s directives regarding the expansion of the Ho Chi Minh City-Long Thanh section of the expressway.

Design rendering of the Long Thanh International Airport – Photo: ACV

The Prime Minister also requested that the Vietnam Airports Corporation (ACV) promptly implement the remaining packages of Component 3. The Ministry of Agriculture and Rural Development was tasked with arranging funds for the construction of the headquarters of the animal and plant quarantine station, ensuring synchronization with the overall project. The Ministry of Transport was assigned to take responsibility and urgently select investors for Component 4, as well as coordinate the construction timeline of Components 1, 2, and 4 with Component 3 implemented by ACV…

With factors such as increased maturity, more experience in large-scale infrastructure projects, mostly completed procedures, substantially finished land clearance, and adequate human resources and machinery at the site, the Prime Minister expressed confidence in having a solid basis to shorten the timeline and substantially complete the project by December 31, 2025.

The Prime Minister emphasized that with the current momentum in the development of the Long Thanh Airport, we are ready to embark on the high-speed North-South railway project, another symbolic infrastructure project in the new era of national development – an era of national advancement.

The Long Thanh International Airport project is invested by the Vietnam Airports Corporation (ACV) with a total estimated investment of approximately VND 336,630 billion (equivalent to US$16 billion). The project is divided into three phases. By 2030, the airport will be able to serve up to 100 million passengers annually with four runways.

The Long Thanh Airport project is a particularly important national project and is considered to have a significant impact on Vietnam’s socio-economic development.

You may also like

The Prime Minister Attends the Plenary Session of the Ho Chi Minh City Economic Forum

The Ho Chi Minh City Economic Forum 2024, themed “Industrial Transformation: A New Driving Force for Sustainable Development in Ho Chi Minh City,” commenced this morning, September 25th.

Vietnam’s Largest Airport Aims for Substantial Completion by Late 2025, With Potential Metro Access?

This is the largest airport project our country has ever seen. An ambitious, groundbreaking development that will transform travel and connectivity for generations to come. With a vision to create a transport hub like no other, this project promises to be a gateway to the world, offering unparalleled convenience and efficiency. A true milestone in our nation’s history, it will leave a lasting legacy and set a new benchmark for airport design and functionality.

The New Long Thanh Airport: Dong Nai Proposes Construction of Second Phase Groundwork

The People’s Committee of Dong Nai province has requested the Prime Minister’s approval for the Ministry of Transport and the Vietnam Airports Corporation to commence land grading work for phase 2 of the project from 2024 to 2025. This request comes as a bid to expedite the construction process, running parallel to the ongoing work of phase 1.

The Ultimate Traffic Solution: Completing the Ring Road by 2025

Prime Minister Pham Minh Chinh has urged for an even more expedited timeline, calling for the completion of the Hanoi Capital Region’s Ring Road 4 section through Bac Ninh by the end of 2025.

Racing with the Long Thanh Airport City

The southern province of Dong Nai is gearing up to maximize the advantages brought by the upcoming Long Thanh International Airport. With the first phase of the airport expected to be operational by September 2026, the province is working diligently to ensure it is well-prepared to capitalize on the opportunities that this major infrastructure project will bring.