The Quang Da Bridge project connects Hoa Khuong ward, Hoa Vang district, Da Nang city with Dien Tien ward, Dien Ban town, Quang Nam province. During the inspection, the representative of the contractor consortium shared that the project has completed 53% of the contract value so far. The total disbursed amount for the project has reached VND 121 billion.
The project aims to be completed by the 50th anniversary of the Liberation of Da Nang City (March 29, 1975 – March 29, 2025) and to commemorate the Party Congresses at all levels for the term 2025 – 2030. It is expected that the Quang Da Bridge and the approach road will be completed by March 2025.
The entire bridge is scheduled to be joined together before March 10, 2025, and technically opened to traffic before March 29, 2025. By that time, the project is expected to have completed 95% of the contract value.
Mr. Phan Van Ton, Chairman of Hoa Vang District People’s Committee, said that the construction progress has basically met the requirements, but the project has faced some obstacles in site clearance.
While the files within the clearance area have been signed for land handover, there are still two outstanding files that need to be completed. Additionally, there are 16 unresolved files along the National Highway 14B that need to be addressed.
The Hoa Vang District Site Clearance Council is focusing on resolving these issues to ensure the technical opening of the road as planned.
Speaking at the inspection, Mr. Nguyen Van Quang, Secretary of the Da Nang Party Committee, stated that this project symbolizes the close relationship between the two localities. It is not only a key project but also a vivid demonstration of cooperation and sustainable regional linkage.
“The investment of the budget from one locality to another in this project is noteworthy and shows a sense of collective responsibility for comprehensive development,” emphasized Mr. Nguyen Van Quang.
According to the Da Nang Party Chief, this project is not just a transportation infrastructure but also a testament to the bond between Da Nang and Quang Nam, promising to boost socio-economic development and strengthen the relationship between the two localities.
The Quang Da Bridge and its approach road project was commenced in December 2023 with a total investment of VND 274 billion. The project is funded by Da Nang City and constructed by the joint venture of Xuan Quang Construction Joint Stock Company and Binh Dinh Transportation Infrastructure Design and Construction Joint Stock Company.
Danang’s Real Estate Market Soars with the Free Trade Zone
The Danang real estate market, particularly the Lien Chieu district, is experiencing a surge in development, fueled by a series of breakthrough growth catalysts. These catalysts include the next-generation free trade zone (FTZ), the Lien Chieu port, and a cluster of high-tech industrial parks. This perfect storm of economic drivers is transforming the area into a thriving hub of activity, attracting investors and businesses alike.
“The Speaker’s Call to Action: Expediting the Creation of a Legal Framework for Emerging Issues to Catalyze Vietnam’s Development”
After 29 and a half days of diligent, scientific, democratic, and responsible work, with a spirit of innovation and a timely resolution of difficulties, bottlenecks, and blockages, the 8th Session of the 15th National Assembly has successfully concluded, having accomplished all its proposed agenda items. This session was marked by a strong focus on economic and social development, national defense, security, and improving the lives of the people.
Peace Province: Strengthening Diplomatic Ties and Economic Cooperation to Attract Investment
Peace Province boasts a diverse range of industries, including agriculture, industry, and tourism, each presenting untapped potential for development. In recent years, the province has actively fostered diplomatic relations and economic collaborations, introducing numerous investment incentives to attract businesses and investors alike.
The Power of 1.3 Million: A Nation-Wide Conference to Internalize and Review the Party’s Resolutions
This morning, the Politburo and the Secretariat held a national conference to promulgate and deploy the implementation of Resolution No. 18-NQ/TW of the 12th Central Executive Committee; review the socio-economic situation in 2024, and discuss solutions to accelerate socio-economic development in 2025, including addressing institutional bottlenecks and constraints.