The Ministry of Transport’s Inspectorate (now the Ministry of Construction) has concluded an inspection on the compliance with legal regulations in the construction management of the Component 2 Project (18km in Dong Nai province) of the Bien Hoa – Vung Tau Expressway Project, under the management of Project Management Unit 85.

Bien Hoa – Vung Tau Expressway Component 2 Layout

According to the inspection conclusion, the contractors proactively mobilized resources and implemented several solutions to organize the construction. However, during the project’s execution, Project Management Unit 85, consulting units, and contractors encountered several issues.

Specifically, in terms of construction quality management, the relevant units failed to promptly update, adjust, and supplement the list of technical standards and guidelines applicable to the project.

Notably, the construction method for prestressed concrete beams (I-beams and super T-beams) lacked calculations for the bearing capacity of formwork; some piles of the D800 soil-cement piers were arranged at the foot of the road embankment and at locations from the abutment cone that did not conform to the approved technical design. Additionally, they replaced beam bridge hooks with prestressed cables and cut the prestressed cables when the concrete strength had not reached 100% as required by the technical design.

The relevant units applied incorrect or missing test indicators during the construction of drilled piles, cement-improved soil piles, concrete work, prestressed concrete beams, and bearings. The records and minutes of acceptance inspections for some works were missing confirmations from the consulting supervision unit; the construction diaries lacked comprehensive information, and there were no acceptance records demonstrating the protection of prestressed reinforcement at the beam ends. Furthermore, the project owner has not reported or clarified the implementation status of four matters noted by the State Council for Construction Acceptance Inspection.

Regarding construction progress management, the project owner approved the overall project schedule later than stipulated in the contract. By the time of the inspection, they had not promptly approved the detailed construction schedule adjustments to align with the project’s actual implementation. The relevant units approved construction drawings and accepted payments for some soil-cement piers that did not adhere to the approved technical design, and for the replacement of beam bridge hooks with prestressed cables. There were also discrepancies in the payments for prestressed concrete beams between the technical guidelines and the contract.

In addition to the issues in construction quality, construction progress, and construction volume management, the inspection conclusion also pointed out problems in occupational safety, construction environment, investment cost management, and other aspects as stipulated in the construction contract.

Specifically, the project owner has not prepared an environmental management plan as required by the approved environmental impact assessment report. During the inspection of occupational safety and environmental sanitation in the project’s construction, the project owner and consulting supervision unit conducted inspections, urged, and reminded the contractors of non-compliance. However, they did not specify deadlines or corrective measures. The mobilization of key personnel (technical, testing, environmental, etc.) and construction equipment by the contractors did not ensure the quantity and quality required by the approved construction plan and schedule. The project owner also failed to promptly inspect and approve replacement and additional personnel. The consulting supervision unit’s monthly reports to the project owner regarding the contractors’ mobilization of machinery and equipment were delayed compared to the contract’s provisions.

The inspection conclusion attributes the aforementioned issues to the responsibility of Project Management Unit 85, consulting supervision units, and contractors.

You may also like

The Metro Line 1: Ben Thanh – Suoi Tien is Ready for Commercial Operations

The Ho Chi Minh City Metropolitan Railway Management Authority (MAUR) has announced that the Ben Thanh – Suoi Tien Metro Line 1 project has reached a significant milestone. With all the necessary requirements met, the project has been approved for commercial operation, marking a pivotal moment for the city’s urban transportation network.

The New and Improved Bien Hoa-Vung Tau Expressway: A $24,000 Crore Venture

The Bien Hoa-Vung Tau Expressway construction investment project, consisting of three sub-projects, is facing significant challenges with regard to land clearance and increasing investment levels, necessitating adjustments to the original investment strategy.

The Sky’s the Limit: Long Thanh Airport Property Soars

The real estate market in Nhon Trach and Long Thanh (Dong Nai) and Ba Ria-Vung Tau is buzzing with positive signals as the year comes to a close. The rapid progress of large-scale transportation infrastructure projects in these areas is a significant contributing factor to this positive momentum.

The First Plastic Carpets on Bien Hoa – Vung Tau Expressway

After almost a year and a half of construction, the Bien Hoa – Vung Tau Expressway project, Component 3, which passes through Ba Ria – Vung Tau province, is receiving its first asphalt layers. The project is striving for technical completion by April 2025.

The Ultimate Traffic Interchange: Unveiling the Largest Expressway Interchange in the Western Region

On the morning of November 20, Deputy Prime Minister Tran Hong Ha, along with a delegation, inspected the construction site where two major expressway projects, Can Tho-Ca Mau and Chau Doc-Can Tho-Soc Trang, intersect.