Just Over 2 Months Left: Travel from Binh Duong to Cu Chi via Ring Road 3

By December 2025, residents will be able to travel seamlessly from Binh Duong to Cu Chi via the Ring Road 3, as confirmed by the Director of the Ho Chi Minh City Transportation Project Management Board.

0
62

On the morning of September 25th, Deputy Prime Minister Mai Văn Chính led Government Inspection Team No. 7 to survey key projects under the Ho Chi Minh City Ring Road 3 initiative.

The team also inspected two major intersections: the Bình Gởi Bridge over the Saigon River and the Tân Vạn Junction, which connects to Hanoi Highway.

According to Lương Minh Phúc, Director of the Ho Chi Minh City Transportation Project Management Board, all component projects of Ring Road 3 have completed 100% of land handover procedures. Contractors are maximizing manpower and machinery to accelerate construction, aiming to open 24.1 km of expressway by December 19th. This includes 14.7 km in Thu Duc, 3 km in former Binh Duong (now part of HCMC), and 6.4 km in Long An (now Tay Ninh province).

24.1 km of Ring Road 3 set to open by year-end. Photo: Duy Khánh

By the same date, 41.4 km of the route will be technically open. The entire 76.3 km Ring Road 3 is slated for completion and full operation by June 30, 2026.

The Director of the City’s Transportation Project Management Board confirmed that by December 2025, residents will be able to travel from Binh Duong to Cu Chi via Ring Road 3.

Trần Hùng Việt, Director of the Binh Duong Transportation Project Management Board (now under HCMC authority), noted that multiple components are being accelerated.

The Bình Gởi Bridge has been joined, but the investor proposes adding a branch costing approximately VND 600 billion from contingency and savings. For the Tân Vạn Junction, a VND 1.7 trillion investment is requested for full development.

For the 15.3 km section overlapping the Mỹ Phước – Tân Vạn route, expansion is proposed to ensure project coherence and maximize efficiency.

Deputy Prime Minister Mai Văn Chính praised the dedication of investors, contractors, and workers. He urged continued resource mobilization, including “3 shifts, 4 teams” operations, to ensure timely, quality, and safe completion.

He emphasized December 19th as the critical deadline for technical opening.

Later that day, the delegation led by Deputy Prime Minister Mai Văn Chính met with HCMC authorities, neighboring provinces, and stakeholders to address challenges and expedite Ring Road 3’s operational launch.

The project spans 76.34 km across HCMC, Dong Nai, Binh Duong, and former Long An, with a total investment of VND 75.378 trillion. Divided into 8 components, it is expected to substantially complete by late 2025.

You may also like

Bình Gởi Bridge Ahead of Schedule, Ring Road 3 Accelerates Towards Completion

The Ho Chi Minh City Ring Road 3 project has successfully completed land clearance, with multiple tenders achieving significant progress. It is on track to open two sections to traffic by December 19, 2025.

RACING TO MEET THE 100-DAY DEADLINE: FINAL STRETCH FOR HO CHI MINH CITY’S RING ROAD 3 PROJECT

Experience the relentless dedication behind the 2025 technical completion of the Ring Road 3 project through Bình Dương. With a 100-day, round-the-clock effort, spanning three shifts, four crews, and working tirelessly through Tet and holidays, this monumental achievement sets a new standard in infrastructure excellence.

Dong Nai Terminates Contractor in Nearly VND 2.6 Trillion Project

Construction progress on several components of Component Project 3, part of the Ho Chi Minh City Ring Road 3 project passing through Dong Nai, has been delayed. One contractor has been liquidated, and the construction workload has been reassigned to another contractor.

A Landmark Achievement: Long Thanh Airport’s Journey to a Safe and Timely Completion

On September 7, Deputy Prime Minister Tran Hong Ha, head of the task force for the Long Thanh International Airport project, inspected the construction progress on-site and worked with the Ministry of Construction, the Vietnam Airports Corporation (ACV), contractors, and relevant ministries and sectors.

Accelerating Progress: Revitalizing the Bien Hoa-Vung Tau Expressway and HCMC’s Ring Road 3 with Efficient Contractor Replacements

Let me know if you would like me to provide any additional revisions or if there is another aspect of the text you would like to focus on.

The authorities in Dong Nai province have issued a directive to fast-track the resolution of contractor issues and the establishment of an updated construction schedule for the Bien Hoa – Vung Tau Expressway and the Ho Chi Minh City Ring Road 3 projects. The directive sets an ambitious deadline of August 2025 for the completion of these tasks, with the aim of ensuring smooth progress towards the technical opening of these vital transportation arteries.