With a total investment of over 7.6 trillion VND, the expansion project of the Yên Bái - Lào Cai expressway segment, part of the Nội Bài - Lào Cai highway, is poised to eliminate the critical bottleneck, standardize the entire route to four lanes, and unlock unprecedented growth for cross-border trade and tourism in the Northwest region.

0
13

According to the Vietnam Expressway Corporation (VEC), the investor of the Noi Bai – Lao Cai Expressway project, the entire route spans 264 km, starting at the Bac Thang Long – Noi Bai interchange (Hanoi) and ending in Bat Xat commune (Lao Cai). This expressway plays a pivotal role in the Kunming – Hanoi – Hai Phong economic corridor, directly connecting with the Kunming – Hekou Expressway (China).

The Hanoi Expressway, operational since 2014, comprises two sections: Noi Bai – Yen Bai and Yen Bai – Lao Cai. Phase 1 of the project revolutionized transportation by reducing travel time from Hanoi to the Lao Cai border gate to just 3.5 hours, down from 7 hours previously. This route has unlocked significant opportunities for trade, investment, and tourism in the Northwest region.

Phase 1 of the Yen Bai – Lao Cai section, part of the Noi Bai – Lao Cai Expressway, has significantly boosted trade, investment, and tourism in the Northwest region. Photo: VEC.

Currently, the Noi Bai – Yen Bai section features 4 lanes with a speed limit of 100 km/h, while the Yen Bai – Lao Cai section has only 2 lanes with a speed limit of 80 km/h. This disparity, coupled with an average annual vehicle growth rate of 10%, threatens to overload the route by 2027.

VEC further notes that the section from Km123+080 to Km244+155 on the Yen Bai – Lao Cai Expressway lacks central median barriers in many areas, posing safety risks. With the 2030 planning aiming to complete the entire route, expanding the Yen Bai – Lao Cai section is an urgent priority, addressing three key objectives.

Specifically, the expansion aims to standardize the route’s scale with the Noi Bai – Yen Bai section, meet growing traffic demands, and foster economic, social, and tourism development while ensuring border security and defense.

As per the investment decision, the Yen Bai – Lao Cai expansion project spans over 121 km. The road will be widened from 2 to 4 lanes, with a 24-meter-wide base and added central median barriers. Scheduled for 2025-2027, the project is set to commence on October 1 and is expected to be substantially completed by 2026, as directed by the Prime Minister.

The Yen Bai – Lao Cai expansion project will upgrade the road from 2 to 4 lanes. Photo: VEC.

The project also includes constructing new left-side bridge units to align with existing bridges; the Dai Viet and Van Xuan bridges will be expanded using tunnel approaches. Additionally, VEC will build a new 530-meter tunnel at Km186, featuring 3 lanes per direction, parallel to the existing tunnel.

“The Yen Bai – Lao Cai Expressway expansion will add a T-shaped interchange at Km165+690 and integrate a smart transportation system (ITS) across the route, including surveillance cameras, a data center, and an ETC toll collection system,” stated a VEC representative. The project will also leverage Building Information Modeling (BIM) and digital solutions for management, construction, and operation.

Upon completion, the upgraded Yen Bai – Lao Cai section will standardize the entire Noi Bai – Lao Cai Expressway to 4 lanes, enhancing transport capacity, reducing pressure on National Highways 70 and 32C, and boosting cross-border trade, particularly with China. Furthermore, the project will promote Northwest tourism, enabling swift and safe connections between Hanoi, Sa Pa, Y Ty, and Bac Ha.

You may also like

Ministry of Construction Updates on Issues Related to the $1.5 Billion Da Nang – Quang Ngai Expressway

The Ministry of Construction has directed the Vietnam Expressway Corporation (VEC) to review and address the concerns raised by voters in Quang Ngai province regarding the Da Nang – Quang Ngai Expressway project.