Rushing to ‘Beat the Sun, Outpace the Rain’ in the Construction of Long Thanh Airport

On December 19th, Long Thanh International Airport will welcome its inaugural flight. In recent days, nearly 14,000 experts, engineers, workers, and laborers, alongside over 3,000 construction machines, have been tirelessly accelerating progress on the site.

0
10

At the Long Thanh Airport project site, thousands of officials, engineers, and workers are accelerating construction to ensure completion in time for the first technical flight on December 19th.

According to Tien Phong’s report, Long Thanh Airport is rushing construction on multiple components of Package 3 (essential airport facilities, Phase 1).

Vietnam Airports Corporation (ACV), the project investor, reports that to execute 12 packages, contractors are mobilizing nearly 14,000 specialists, engineers, workers, and over 3,000 construction equipment units, operating hundreds of work fronts to expedite progress.

At Package 5.10, constructing the Long Thanh Airport passenger terminal, work is intensely underway. This is the most critical package of the entire project, likened to the heart of Long Thanh Airport.

Inside the passenger terminal, workers are installing escalators, elevators, staircases, and fire prevention systems.

Package 5.10 (passenger terminal) has allocated 4,914 personnel and over 1,000 pieces of equipment.

Construction of the pipe casing system at Long Thanh Airport.

The wing section’s architectural roof is nearly complete.

The passenger terminal wing is being rushed to completion.

Joint ventures have mobilized hundreds of work fronts.

Packages for police and customs facilities are also entering the final stages.

Long Thanh Airport’s runway is ready for the first technical flight on December 19th.

The airport’s fuel storage area is also under accelerated construction.

Long Thanh Airport, located in Long Thanh commune, Dong Nai province, spans over 5,000 hectares. The total investment is estimated at over $16 billion, divided into three phases. Phase 1 costs over $5.4 billion, with a capacity of 25 million passengers and 1.2 million tons of cargo annually.

You may also like

Vietnam’s $16 Billion Mega Project Nears Milestone: Unveiling a 390km+ Network of Ring Roads, Highways, and Three Metro Lines

Ho Chi Minh City and Dong Nai Province are mobilizing all resources to simultaneously implement a series of critical transportation infrastructure projects, directly connecting to the Long Thanh International Airport—a national key project.

Proposed Clarification: Identifying the Executing Authority for Phú Mỹ 2 Bridge and Two Inter-Regional Projects

The Phú Mỹ 2 Bridge project has been identified as a critical initiative to significantly reduce travel time between Ho Chi Minh City and Long Thành International Airport. It is expected to be presented to the Ho Chi Minh City People’s Council for approval during the upcoming session.

Unveiling Southeast Asia’s Tallest Air Traffic Control Tower at Long Thanh Airport

The air traffic control tower stands as the nerve center for flight operations at Long Thanh International Airport in Dong Nai. This critical structure is part of the second component project of the Long Thanh Airport, spearheaded by the Vietnam Air Traffic Management Corporation as the primary investor, with a total investment of 3.5 trillion VND.

ACV Proposes to Lead Phase 2 of Long Thanh Airport Project with Estimated Investment of VND 80,000 Billion

With Phase 1 construction accelerating and aviation demand soaring, Long Thanh Airport is gearing up for its next stage of development. ACV, the driving force behind this mega aviation project, has officially proposed continuing as the lead investor for Phase 2.