Massive $100 Million Highway Connecting Hanoi’s Ring Roads Nears Completion

The arterial route connecting Ring Road 2.5 to Ring Road 3 in Hoang Mai District is undergoing accelerated construction to alleviate chronic congestion in southern Hanoi. Upon completion, this new thoroughfare will establish an alternative traffic flow, significantly easing transportation burdens and reducing travel times for residents.

0
50

The $100 Million Road Project Connecting Hanoi’s Ring Roads is Nearing Completion

The Minh Khai – Vĩnh Tuy – Yên Duyên road project, connecting Ring Road 2.5 to Ring Road 3 in Hoàng Mai District, spans 2.07km with a width of 40m. Approved in October 2023 by Hanoi People’s Committee, the project’s total investment is VND 370 billion, including VND 221 billion for construction and VND 85 billion for land clearance. The project is managed by the Hoàng Mai Infrastructure Investment Project Management Board.

Half of the road section from Gamuda Urban Area to Hoàng Mai Residential Area, approximately 1km long, is under construction with foundation and underground utilities being installed.

The remaining section from Hoàng Mai Residential Area to Vĩnh Hoàng Urban Area, passing through agricultural land, has yet to begin construction. Locals are currently cultivating crops on the uncleared land.

The segment through Hoàng Mai Residential Area is undergoing foundation work, while the section connecting to Ring Road 2.5 remains pending.

Located in a densely populated area with heavy traffic, the project prioritizes construction safety.

Half of the road has been completed and is temporarily in use, connecting Gamuda Urban Area for several years.

Construction crews are working diligently to meet deadlines, leveraging favorable weather for land leveling, compaction, and underground pipe installation.

Designed as an urban standard road, it features a 40m width, 60km/h speed limit, central median, and integrated utilities. The project requires approximately 65,000m² of land acquisition.

The road linking Ring Road 2.5 to Ring Road 3 in Hoàng Mai District is progressing rapidly. Upon completion, it will enhance connectivity, ease traffic congestion, and improve travel convenience for residents.

You may also like

New Developments for Hanoi’s 1.6km Road Project After Nearly a Decade of Stagnation Since 2014 Groundbreaking

The construction of the 2.5 Road project (Đầm Hồng – National Highway 1A section) has now surpassed 70% completion, with expectations to reach full completion by Q1 2026.

South Korean Firm Plans $60 Million International Resort Development in Gia Lai Province

“Leading Korean conglomerate proposes a $60 million investment in two world-class golf and resort complex projects, spanning 550 hectares. With a vision to pioneer the development of infrastructure and tourism in Gia Lai, the projects aim to become a landmark destination, offering unparalleled experiences to visitors seeking luxury and leisure.”

The Potential Districts and Wards to be Established When Thua Thien-Hue Becomes a Central City

The Ministry of Construction has approved the establishment of Phu Xuan and Thuan Hoa districts and their respective wards, in the soon-to-be-centrally-governed city of Thua Thien – Hue.