On August 15, Deputy Minister of Transport Nguyen Duy Lam led an inspection team to review the progress of the Van Phong – Nha Trang Expressway project.

The investor, contractor, and Khanh Hoa provincial authorities pledged to resolve obstacles and accelerate construction to aim for an early launch by April 30, 2025, eight months ahead of schedule.

According to Project Management Unit 7 (the project investor), contractors have mobilized 30 construction units. The project has achieved a production value of VND 4,704 billion out of VND 7,132 billion, reaching 66% of the contract value.

Land clearance for the main expressway route is almost complete. However, approximately 2.4 km remain unfinished due to technical infrastructure issues and local land clearance complications.

Deputy Minister of Transport Nguyen Duy Lam and Vice Chairman of the Provincial People’s Committee Tran Hoa Nam inspect the Van Phong – Nha Trang Expressway project

To meet the goal of completing the project eight months ahead of the Prime Minister’s directive, the Project Management Unit 7 requested the Ministry of Transport to urge the People’s Committee of Khanh Hoa Province to direct the People’s Committees of Ninh Hoa Town and Van Ninh District to resolve pending issues and hand over the site to the contractor before August 30.

The Van Phong – Nha Trang Expressway project has approximately 2.4 km remaining due to technical infrastructure and land clearance issues

At the inspection, Deputy Minister Nguyen Duy Lam praised the Van Phong – Nha Trang Expressway project for having the best progress among the 12 expressway components under construction nationwide. He urged the investor and contractor to take advantage of favorable weather conditions to accelerate construction and ensure the project’s completion by April 30, 2025.

Deputy Minister Nguyen Duy Lam requested the provincial authorities to direct local authorities and related departments to actively coordinate and support the investor in acquiring the remaining land for construction.

The Van Phong – Nha Trang Expressway project has a total length of approximately 83.35 km, starting at Km 285+000 at the intersection of Co Ma Tunnel in Van Tho Commune, Van Ninh District, and ending at Km 368+000, connecting with National Highway 27C in Dien Tho Commune, Dien Khanh District. It will also connect with the Nha Trang – Cam Lam Expressway.

The total investment for the project is estimated at VND 11,808 billion. The total land clearance area is over 616.2 hectares, affecting 2,792 households, of which approximately 280 households need resettlement. Additionally, 20 technical infrastructure systems must be relocated, including 164 intersection points.

You may also like

High-speed Fever from Bien Hoa to Vung Tau through Dong Nai Province

After 7 months of construction, the Biên Hòa-Dồng Nai expressway project is still facing challenges with land clearance.

Nghệ An: Accelerating the progress of land clearance for the 500kV circuit project

Nghệ An Province is determined to complete the ground leveling for the 500kV circuit 3 project by February 2024 and the corridor for the line by March 2024, in accordance with the directives of the Prime Minister.

Over $18 trillion roads in Binh Duong will feature two rest stops

In addition to calculating land use adjustments, Binh Duong province is planning to acquire additional land to build two rest stops along the Ho Chi Minh City Ring Road 4. The project has a total investment capital of over 18,000 billion VND for the section passing through Binh Duong province.

Put your skills to the test with big projects

Ho Chi Minh City is currently in the midst of rapidly implementing a series of major projects, with the goal of disbursing 10%-12% of the total public investment capital, amounting to nearly VND 80 trillion, in the first quarter of 2024.