4 traffic projects
Thuan An Group has been and is constructing in Hanoi including: Thang Long Bridge deck repair project, Vinh Tuy 2 Bridge project (key project); Project building An Duong intersection flyover – Thanh Nien road; Upgrading and widening Nghi Tam – Au Co road (project of An Duong intersection flyover construction project – Thanh Nien road phase 2 – key and urgent project). In which, the Nghi Tam – Au Co road upgrade and expansion project is currently under construction; the remaining 3 projects have been completed and put into use.
Specifically, with the Thang Long Bridge deck repair project, the project was invested by the Vietnam Road Administration – Ministry of Transport, Thuan An Group was one of the project contractors, the project was completed in 2021 and handed over to Hanoi for management and traffic organization.
For the Vinh Tuy 2 bridge project, under the investorship of Hanoi Transport Construction Project Management Board ( Hanoi Transport Board), Thuan An Group jointly with Cau 7 Thang Long Joint Stock Company won the bid and implemented the bidding package number 02, the bid package has a value 289 billion VND; currently the Vinh Tuy 2 bridge project has been completed and put into use in 2023.
In the An Duong intersection flyover construction project – Thanh Nien road, invested by Hanoi Transport Department, Thuan An Group won the bid package No. 12 worth about 100 billion VND; Currently, the project has also been completed and put into operation in 2018.
To expand the Au Co road section from Nghi Tam to Nhat Tan bridge, reduce traffic jams and create synchronization with the infrastructure of Nghi Tam road and An Duong flyover just inaugurated, in 2018 the Hanoi City People’s Committee agreed to allow the investor, the Transport Department, to implement the project to build a flyover at the An Duong – Thanh Nien road intersection, phase 2. The project includes the following main works: Digging the Red River embankment, building a retaining wall to widen Au Co road from Nghi Tam to Nhat Tan bridge, 3.7 km long. The total investment of the phase of the project is 544 billion VND, the construction time is from 2018 to 2020.
However, to date, according to PV Tien Phong , by 2020, more than 3 years, the Nghi Tam – Au Co road upgrade and expansion project is still not completed. At the construction site of bid package No. 40 from Xuan Dieu intersection to Lac Long Quan intersection of the consortium of 3 contractors, including Thuan An Group, it is still messy.
There was a wage debt to workers
Regarding the current project progress and construction status, a representative of the Hanoi Transport Department (investor) said that the project has completed 75% of the workload, with bid package 40 completed 70% (the lowest completion rate). in the construction bid packages in the project – PV).
With the construction on site, the Traffic Department said that the bid packages, including bid package No. 40, workers and construction machinery are still maintained and uninterrupted; Currently, the investor is urging contractors to speed up construction, achieving the plan to open traffic for the entire project by June 30, 2024.
Explaining the reason for the delay in the Au Co road expansion project, the representative of the Traffic Department said that the project had to adjust the design many times at the request of the Ministry when applying the regulations according to the Dyke Law; Along with that, every year during the flood season, the project has to stop construction for about 4 months (from June to September); during the construction, the contractor faced many difficulties due to the high price of materials at the time of building the project tender documents with the construction time at …
Information on the use and exploitation process of the above works, the investor and the Hanoi Traffic Construction Joint Stock Company 2; Hanoi Traffic Construction Joint Stock Company 3 – two units taking over, exploiting and maintaining the works said that the works are still being used effectively and no problems have been found.
However, at the construction site of the An Duong intersection flyover construction project – Thanh Nien road (phase 1), as recorded by reporters, after the project was opened to traffic and put into use for more than 1 year, many Construction workers at bid package No. 12 constructed by Thuan An Group have filed a complaint with the authorities that they have not received their wages during the construction period at the project.
The investor and the Hanoi Transport Department have confirmed this and said that after learning about the incident, the investor has worked with the contractor, Thuan An Group, thereby determining that the incident occurred because Thuan An Group’s subcontractors owed wages. salary workers, from this fact the investor has requested Thuan An Group to work with the subcontractors to resolve and resolve the incident.