"Vietnam's Ministry of Transport has issued Document No. 9228 in response to voters' requests from Ho Chi Minh City regarding the acceleration of key project completion timelines."

0
50

In response to inquiries from voters, the Ministry of Transport has provided an update on the progress of the Long Thanh International Airport project. The Ministry confirmed that the Prime Minister has approved four investment projects for the construction of the airport’s first phase, with a total investment of VND 109,111,742 billion (USD 4,664,89 million). These projects include:

(1) Project Component 1 – Government Management Agency Facilities

(2) Project Component 2 – Air Traffic Control Facilities

(3) Project Component 3 – Essential Airport Facilities (with ACV as the investor and a total investment of VND 99,019,26 billion)

(4) Project Component 4 – Other Works

To expedite the process, the Ministry of Transport, the investor, contractors, and consulting units have focused their resources on reviewing, researching, and developing construction plans. As a result, they have successfully shortened the timeline for the Passenger Terminal and Runway projects by nearly three months compared to the contractual schedule.

The goal is to complete the Passenger Terminal before August 31, 2026, and put it into operation on the occasion of the National Day celebration on September 2, 2026. Simultaneously, the construction timeline for the Runway has been reduced by three months, ensuring its technical operation before April 30, 2025, to commemorate the 50th anniversary of the liberation of Southern Vietnam and the reunification of the country.

The Long Thanh International Airport is a key national project and a special-grade construction, holding significant importance for the development of the Southern Key Economic Zone and Vietnam as a whole.

Additionally, the Ministry provided an update on the progress of the construction of Terminal 3 at Tan Son Nhat International Airport. Due to challenges in land clearance, the project could only commence in December 2022, and the main contract for the construction of Terminal 3 was signed on August 31, 2023. The contract took effect on October 15, 2023, with a construction period of 20 months, aiming for completion by June 15, 2025. Currently, the structural work has been completed, and the project is in the process of architectural finishing, construction, interior design, and equipment installation, with an overall progress of approximately 70%.

The investor ACV, contractors, and consulting units are committed to focusing their resources and optimizing the construction schedule to shorten the timeline by two months compared to the contract. They are determined to complete the project by April 30, 2025, marking the 50th anniversary of the liberation of Southern Vietnam and national reunification.

You may also like

Tet at the Large Plaza Airport in Long Thanh

Staying at work throughout Tet, thousands of workers at Long Thanh International Airport are filled with excitement as the surroundings are adorned with an abundance of apricot blossoms, chrysanthemums, and peach blossoms.

Tan Son Nhat Airport is quite “unusual” on the 30th Lunar New Year.

On the morning of February 9th (the 30th day of Tet), both the inside and outside areas of Tan Son Nhat Airport in Ho Chi Minh City were smooth and clear. On the final day of the Year of the Cat, the airport is expected to operate 655 flights with over 100,000 passengers.

“1,000 engineers and workers continue construction throughout Tet at the massive construction site of Long Thanh airport”

With a workforce of around 1,000 skilled individuals and over 100 construction machines and equipment, we are dedicated to ensuring the progress of the Long Thanh Airport project (in Dong Nai province) through the Lunar New Year holiday in 2024.

Unbelievable Tet Flight Tickets from Tan Son Nhat Airport on the 30th Tet

The number of passengers at Tan Son Nhat Airport on the 30th Tet is expected to decrease significantly, but passengers can still purchase same-day tickets at lower prices compared to previous days…

Prime Minister Pham Minh Chinh directs the progress of Long Thanh Airport and Terminal 3 at Tan Son Nhat Airport

The Prime Minister has urged to accelerate the construction progress of the Long Thanh International Airport (LTIA) project to be completed within the first 6 months of 2026, and the T3 terminal of Tan Son Nhat Airport to be completed by April 30th, 2025.