Vân Phong – Nha Trang Highway Accelerates Progress, Speeding Towards Completion

The progress of the Vân Phong - Nha Trang expressway project is 2% ahead of schedule, with an expected completion in 2025 and operation starting in 2026.

0
141

The Van Phong – Nha Trang Expressway project has a total investment of over VND 11,808 billion, with a total length of about 83.35 km, and started construction on January 1, 2023. The project is divided into two packages, XL01 and XL02, with the basic completion expected in 2025 and put into operation from 2026.

Sections of the Van Phong – Nha Trang expressway have been paved with asphalt. Photo: L.H.

The two aforementioned contracts are implemented by a consortium of Lizen Joint Stock Company, Phuong Thanh Transport Investment and Construction Company, Hai Dang Joint Stock Company, and E&C Construction Investment Joint Stock Company; A consortium of Son Hai Group Limited Liability Company – Vietnam Import and Export and Construction Joint Stock Company.

The machinery of the contractors is constructing a section of the project through Dien Khanh district. Photo: L.H.

Days close to the 2024 Lunar New Year, the contractors are still rushing to work on the Van Phong – Nha Trang expressway construction site. The overall progress of the project is faster than the set plan by 2%. Currently, the project has also mobilized 39 construction sites (24 road construction sites, 15 bridge construction sites) with a total of 1,323 laborers and 658 construction equipment of all kinds. In the photo, the contractor is carrying out the project through Ninh Hoa town. Photo: L.H.

The leaders of Project Management Board 7 (investor of the Van Phong – Nha Trang expressway) said that up to now, localities in Khanh Hoa province have handed over the ground for 99.6%. There is currently only 0.32km in Ninh Hoa province that has not been handed over (accounting for 0.4%) and the power infrastructure systems have not been fully relocated. Photo: L.H.

Along the route, there have been 2,774 households (100%) handing over land to the construction unit. Up to the present time, completed construction of 6/6 resettlement areas and organized plots, drawn lots for 203/203 households. In the photo, the contractor is having workers construction at an intersection in Van Ninh district. Photo: L.H.

In the construction and installation contracts, the contractors have mobilized 42 construction sites with a total of 1,836 laborers and 943 construction equipment of all kinds. The accumulated output has reached over VND 2,625 billion contract value (2% faster than the adjusted plan to complete ahead of June 30, 2025). Photo: L.H.

Currently, package XL01 has achieved 36.3% of the contract (1.1% ahead of the plan), and package XL02 has achieved 37.5% of the contract (3.2% ahead). The disbursed capital in 2023 is over VND 4,131 billion (nearly 100% of the assigned capital plan). Photo: L.H.

The contractor is paving asphalt at multiple sections of the route near the Giap Tet Giap Thin. Photo: L.H.

The Van Phong – Nha Trang expressway project across Khanh Hoa province has its starting point connecting to the Cau Ma tunnel (Van Ninh district) and its end point connecting to the Nha Trang – Cam Lam expressway (Dien Khanh district). The route is 83.35km long, passing through the districts of Van Ninh, Dien Khanh, Khanh Vinh, and Ninh Hoa town. The construction scale of the project is a complete expressway with a design speed of 120 km/h, a roadbed width of 32.25m, and a 6-lane scale.
SOURCEcafef
Previous articleProjects Connecting the Economic Hub of Tay Nguyen
Next articleVietnam ranks in the top 10 travel markets of Singapore.